PREPARING THE CONDENSATE DRAIN
The condensate produced by the POWER PLUS boiler
during normal operation must be drained at atmospheric
pressure, i.e. by dripping into a siphoned drain system.
This should be installed as follows:
- Install a condensate collection tank at the condensate
drain.
- Connect the condensate collection tank to the drains
via a siphon.
- Install a neutraliser if required by law.
b
The condensate collection tank must be made and
installed in compliance with applicable standards.
b
Specific pipes for condensing boilers must be
used. For installation, follow the instructions
provided with the kit.
Drain trap along the drain pipe
If the vertical or horizontal section of the drain pipe
needs to be extended by more than 4 metres, a drain
32
trap must be installed at the foot of the pipe.
The useful height of the drain trap must be at least 300
mm. The discharge of the drain trap must then be con-
nected to the sewerage system.