HORIZONTAL
INSTALLATIONS
Install the vent system according to the
manufacturer's instructions included
with the components.
1) Set the unit in its desired location. Check to
determine if wall studs or roof rafters are in
the way when the venting system is at-
tached. If this is the case, you may want to
adjust the location of the unit. Rough in the
gas preferably on the right side of the unit
and the electrical (junction block is on the left
side) on the left.
2) Direct Vent pipe and fittings are designed
with special twist-lock connections to con-
nect the venting system to the appliance flue
outlet. A twist-lock appliance adaptor is an
available option that must be used in con-
junction with the Simpson Dura-Vent Direct
Vent GS system.
3) Put a bead of silicone inside the outer section
of the adapter and a bead of Mill Pac on the
inner collar. Slip the adapter over the exist-
ing inner and outer flue collar and fasten to
the outer collar only with the 3 supplied
screws (drilling pilot holes will make this
easier). Level the fireplace and fasten it to
the framing using nails or screws through
the nailing strips.
4) Assemble the desired combination of pipe
and elbows to the appliance adaptor and
twist-lock for a solid connection.
Note:
a) Twist-lock procedure: Four indentations,
located on the female ends of pipes and
fittings, are designed to slide straight
onto the male ends of adjacent pipes and
fittings, by orienting the four pipe inden-
tations so they match and slide in to the
four entry slots on the male ends, Dia-
gram 1. Push the pipe sections com-
pletely
together, then twist-lock one
section clockwise approximately one-
quarter turn, until the two sections are
fully locked. The female locking lugs will
not be visible from the outside, on the
Black Pipe or fittings. They may be locat-
ed by examining the inside of the female
ends.
Diagram 1
Note: Apply sealant "Mill-Pac" to inner
pipe and high temperature sili-
cone sealant to outer pipe on eve-
ry twist-lock joint.
FPI P36D Zero Clearance Direct Vent Gas Fireplace
b) Horizontal runs of vent must be sup-
ported every three feet. Wall straps are
available for this purpose.
5) Mark the wall for a 10" x 10" square hole.
The center of the square hole should line up
with the centerline of the horizontal pipe.
Cut and frame the 10 inch square hole in the
exterior wall where the vent will be termi-
nated. If the wall being penetrated is con-
structed of non-combustible material, i.e.
masonry block or concrete, a 7"(178mm)
dia. (7-1/2"(191mm) dia. for flex) hole is
acceptable.
Note:
With
D u r a - V e n t ,
the
mini-
mum height
is achieved
by installing
o
a 90
elbow
directly
to
the
rigid
pipe adaptor.
Diagram 2
Note:
a) The horizontal run of vent must be level,
or have a 1/4 inch rise for every 1 foot
of run towards the termination. Never
allow the vent to run downward. This
could cause high temperatures and may
present the possibility of a fire.
b) The location of the horizontal vent termi-
nation on an exterior wall must meet all
local and national building codes, and
must not be blocked or obstructed. For
External Vent Terminal Locations, see
diagram on page 20.
c) Snorkel Terminations:
For installations requiring a vertical rise
on the exterior of the
building, 14-inch and
36-inch tall Snorkel
Terminations are avail-
able, as well as the
standard Riser
Vent. Follow the
same instal-
lation pro-
cedures as
used
for
s t a n d a r d
Horizontal
T e r m i n a -
tion. NEV-
ER install
the snor-
kel upside
down.
Diagram 3
INSTALLATION
Note: Riser Vent
is only for use
in above grade
terminations.
Diagram 3a
*Diagrams 3 & 4: As specified in CGA B149
Installation Code. Local codes or regula-
tions may require different clearances.
Below Grade Installation
If the Snorkel Termination must be installed
below grade, i.e. basement application, proper
drainage must be provided to prevent water
from entering the Snorkel Termination. Refer to
Diagram 4. Do not attempt to enclose the Snor-
kel within the wall, or any other type of enclo-
sure.
Diagram 4
NOTE: For Snorkel terminations in ABOVE
grade installations, follow nation-
al or local code requirements.
6) The arrow on the vent cap should be
pointing up. Insure that the 1-1/2" clear-
ances to combustible materials are main-
tained (Diagram 4). Install the termination
cap.
31

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

P36d-lp

Table of Contents