Transport the switchgear by means of a crane or a fork-lift truck.
The transport units are screwed on the wooden pallets with transport angles or directly
in the switchgear subframe.
Fig. 35: Transport unit fixed on wooden pallet with transport angle (view from the left)
Remove the PE foil; if required, remove seaworthy or latticed crate before.
Remove the front cable compartment cover from the subframe of the switchgear.
Remove the fixing screws from the transport angles / pallet.
Remove the transport angles.
If the switchgear cannot be lifted directly from the wooden pallet onto its mounting
position, please proceed as follows:
Lower the transport units by means of the lateral transport angles onto roller pads
(reinforced rollers) or tubes.
Lift the switchgear at the side edges with roller crowbars and slowly lower it onto
the mounting position.