78 Redundant system upgrade
4
5
6
7
Deploy and start secondary network elements
Deploy and start secondary network elements from the MCS Management
Console.
Approximate time estimate = 15 minutes
The following table shows how secondary network elements are deployed
on secondary servers.
Table 4
Network element deployment on secondary servers
Server
MgmtSvr2
SESM2
IPCM/Prov2
Deploy and start network element instances on secondary servers in the
following order:
1. Secondary System Manager
2. Primary Accounting Manager
3. Secondary Session Manager
4. Secondary Provisioning Manager (Deploy only. Do not start until the
5. Secondary IP Client Manager
Copyright © 2007, Nortel Networks
.
unzip <load_name>.zip
Change the directory:
cd /var/mcp/loads/<load_name>/install_scripts
Copy the upgrade script:
cp bin/* /var/mcp/exlab
Change the directory:
cd /var/mcp/exlab
Edit the installation properties file installprops.txt as follows:
ne.load = <load_name>
Components
Secondary System Manager, Primary Accounting Manager
Secondary Session Manager
Secondary Provisioning Manager, Secondary UFTP, Secondary IPCM
online Help upgrade is complete, as described in the next section.)
Nortel Multimedia Communication Server 5100
MCS Upgrades—Maintenance Releases
NN42020-303 01.08 Standard
Release 4.0 10 August 2007
—End—