92 Redundant system rollback
3
4
Stop the secondary System Manager
Stop the System Manager on the secondary System Manager Server.
Approximate time estimate = 5 minutes
Procedure 75
Stopping the secondary System Manager
Step
1
2
3
Restore, deploy, and start primary network elements
Restore, deploy, and start primary network elements from the MCS Management
Console.
Approximate time estimate = 15 minutes
Restore, deploy, and start network elements on primary servers in the
following order:
1. Secondary Accounting Manager
Copyright © 2007, Nortel Networks
.
cd /var/mcp/exlab
Restore the primary System Manager:
./smUpgrade.pl -p installprops.txt -start
Log off as nortel:
exit
Action
Log on to the secondary System Manager Server as nortel.
Change the directory:
cd /var/mcp/run/MCP_9.1/SM_1/bin
Stop the System Manager:
./neStop.pl
Nortel Multimedia Communication Server 5100
MCS Upgrades—Maintenance Releases
NN42020-303 01.08 Standard
Release 4.0 10 August 2007
—End—
ATTENTION
—End—
ATTENTION