10 Attempt to raise the primary boom.
Result: The boom should not raise.
The primary boom will not raise
until the axles are fully extended.
11 Remove the key from the main key switch and
insert the key into the service bypass/recovery
key switch.
The main key switch should
remain in the ground control
position.
12 Turn the service bypass/recovery key switch to
the service bypass position.
13 Raise the boom.
Result: The boom should raise.
14 Remove the key from the service
bypass/recovery key switch and insert the key
into the main key switch.
15 Turn the main key switch to the off position.
16 Remove the key from the main key switch and
insert the key into the service bypass/recovery
key switch.
17 Turn and hold the service bypass/recovery key
switch to the recovery position.
Result: The boom should return to the stowed
position.
18 Turn the service bypass/recovery key switch to
the run position.
19 Remove the key from the service
bypass/recovery key switch and insert the key
into the main key switch.
20 Turn the main key switch to the off position.
21 Close the turntable side cover.
Part No. 62401
Section 4 • Scheduled Maintenance Procedures
B-14
Test the Ground Control
Override
A properly functioning ground control override is
essential to safe machine operation. The ground
control override function is intended to allow ground
personnel to operate the machine from the ground
controls whether or not the red Emergency Stop
button at the platform controls is in the on or off
position. This function is particularly useful if the
operator at the platform controls cannot return the
boom to the stowed position.
1 Push in the red Emergency Stop button at the
platform controls to the off position.
2 Start the engine from the ground controls.
3 At the ground controls, operate each boom
function through a partial cycle.
Result: All boom functions should operate.
S-100 & S-105 & S-120 & S-125
CHECKLIST B PROCEDURES
Genie requires that this procedure
be performed every 250 hours or
quarterly, whichever comes first.
The boom will not raise past
horizontal and the boom will not
extend more than 12 inches /
30.5 cm unless both axles are fully
extended.
4 - 31