Fujitsu Airstage J-II Series Design & Technical Manual page 594

Small vrf system
Table of Contents

Advertisement

In the case of AOU60RLAVM
● It is necessary to change a connection pipe diameter by using Reducer.
(1) Reducer must be brazed outside of the outdoor unit.
(2) Distance between 3-Way-Valve and Reducer ≤ 3 ft. (1m)
(3) The part of Reducer do insulation processing after brazing .
Connection pipe (Gas)
(Pipe outside dia.: 3/4 in. (19.05 mm))
z Handling precautions for the valves
● Mounted part of Blank cap is sealed for protection.
● Fasten blank cap tightly after opening valves.
Blank cap
[in. (mm)]
1/4 (6.35) dia.
3/8 (9.52) dia.
1/2 (12.70) dia.
5/8 (15.88) dia.
3/4 (19.05) dia.
Operating the valves
● Use a hexagon wrench (size 3/16 in. (4 mm)).
● Opening (1) Insert the hexagon wrench into the valve shaft, and turn it counterclockwise.
(2) Stop turning when the valve shaft can no longer be turned. (Open position)
● Closing
(1) Insert the hexagon wrench into the valve shaft, and turn it clockwise.
(2) Stop turning when the valve shaft can no longer be turned. (Closed position)
Opening direction
Opening direction
Liquid pipe
Brazing
3 ft. (1m)
or less
Connection pipe (Gas)
(Pipe outside dia.: 5/8 in. (15.88mm))
Reducer
(accessory)
Example. Case of front connection
Tightening torque
[N·m]
20 to 25
20 to 25
25 to 30
30 to 35
35 to 40
Hexagon wrench
Seal (blank cap installation portion)
Gas pipe
- (06 - 30) -

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Airstage aou36rlavmAirstage aou48rlavmAirstage aou60rlavmAirstage auua4tlav1Airstage auua7tlavAirstage auua9tlav ... Show all

Table of Contents