Setup
Connect Heated
Heated Hose
Connect
Connect
Heated
See the heated hose manual for detailed instructions.
1. For proportioners with termination box (TB):
a. Connect hose power wires to terminal block
(T) on termination box (TB). Remove box
cover and loosen lower strain relief (E).
Route hose wires (V) through the box strain
relief and fully insert into terminal block (T). A
and B hose wire positions are not important.
Torque to 35–50 in-lb (4.0–5.6 N·m).
b. Fully tighten strain relief screws and replace
cover.
Figure 11 Termination Box
30
Hose to to to Proportioner
Proportioner
Hose
Proportioner
2. For proportioners with electrical splice connectors
(S):
a. Connect hose power wires to electrical splice
connectors (S) from proportioner. Wrap
connections with electrical tape.
Figure 12 Electrical Splice Connectors
3. Connect FTS cable connectors (R). Fully tighten
RTD connectors, if provided.