Preparing the Equipment Racks

Following your installation plan, use a tape measure and marking pen to measure
and mark space on each equipment rack for each E-series router component.
Horizontal spacing should follow NEBS requirements. If you choose not to install
a plenum, be sure to include 2 U of space between each chassis to allow for
proper exhaust. A plenum, however, is highly recommended.

Installing the Router

To complete the installation of the router in a rack, you need:
WARNING: Three people are required to install the E-series router in a rack: two to
lift the system into position and one to screw it to the rack.
WARNING: All persons handling an E-series router should wear an antistatic device.
To install the router in the rack:
1.
NOTE: One person should stand on the left side of the router, and another should
stand on the right side when lifting.
2.
3.
Figure 18 illustrates a distribution rack with one ERX-310 router, one
ERX-7xx model, and one ERX-14xx model installed.
32
Rack-Mounted Installation
A Phillips screwdriver
Depending on the router, up to eight 10-32 x 3/8 Phillips screws (provided with
the router) for each router to be installed
Position the router in its designated location in the equipment rack. Make
sure the holes of the mounting brackets align evenly with the holes of the
equipment rack on both sides.
Starting at the bottom, secure the router in the equipment rack by using the
10-32 x 3/8 Phillips screws.
Connect the necessary cables (see "Cabling E-series Routers" on page 51, for
instructions on installing the cables).