Thermal Insulation - Buderus Logano GE315 Installation And Maintenance Instructions Manual

Cast iron sectional boiler for oil or gaspressure jet burners
Table of Contents

Advertisement

2
Installation

2.7.2 Thermal insulation

The thermal insulation supplied corresponds to the
respective boiler size (Tab. 1). Arrange the thermal
insulation according to the Fig. 32 illustration shown
on the boiler block.
At the lower boiler area push the insulating material
under the boiler block. The boiler section feet are set
into the cut-outs of the thermal insulation.
Boiler size
Boiler segments
105
140
170
200
230
Tab. 1
Thermal insulation dimensions
Slide the thermal insulation for the rear section
(Fig. 33, [2]) onto the flue gas coupling. Ensure that
the cut-out for the boiler flow and return points
upwards.
Hook the thermal insulation for the rear section into
the upper cross support bracket using two spring
hooks (Fig. 33, [1]).
Close the gap below the flue gas coupling with spring
hooks (Fig. 33, [3]).
26
L
5
840
6
1000
7
1160
8
1320
9
1480
Logano GE315 - We reserve the right to make any changes due to technical modifications
Fig. 32 Thermal insulation
V: Front (boiler front)
H: Rear (boiler back)
1
Fig. 33 Installation of thermal insulation at the rear section
V
H
2
3

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents