System start-up
3.2

Making the system operational

Observe the following during commissioning:
Prior to commissioning vent the heating system via
radiators and air vents.
Check, whether the hot gas baffle plates have been
correctly inserted.
3.3
Commissioning the control device
Please check in the documentation of the series 4000
control device, which you are using, how to commission
the control device.
3.4
Start up the burner
Proceed with the commissioning of the burner in
accordance with the installation and maintenance
instructions included with the burner.
Complete the commissioning report included in the
burner documentation.
You may raise the flue gas temperature, if you discover
during measurements for the commissioning report, that
the flue gas temperature is too low for the type of
chimney used (danger of condensation).
36
Logano GE315 - We reserve the right to make any changes due to technical modifications
Fig. 52 Check the location of the hot gas baffle plates