Return to the menu MANUAL TEST and stop ADD.HEAT 1 by
setting the value back to 0.
29.
Repeat steps 26 to 28 for ADD.HEAT 2 and ADD.HEAT 3.
30.
Stop the circulation pump by setting the value to 0.
Test fuse protection
n
31.
Start the circulation pump by setting the value CIRC.PUMP to 1
32.
Start the compressor by setting the value HEATPUMP to 1.
33.
At the same time, start the auxiliary heating power stages
available to check that the fuse protection can withstand full
power operation.
34.
Stop the auxiliary heating power stages and the compressor
by setting the value back to 0.
35.
Stop the circulation pump by setting the value to 0.
Test the outdoor unit for Geysir Air
n
36.
Start the defroster shunt by setting the value SHUNT DEFR to 1.
37.
Start the fan at low speed by setting the FAN L value to 1.
Check that the fan runs at low speed.
38.
Start the fan at high speed by setting the FAN H value to 1.
Check that the fan runs at high speed.
Exit test operation
n
39. Set the value for MANUAL TEST to 0.

10.3. COMMISSIONING

Starting circulation pumps manually
n
If any of the circulation pumps do not start, it may need to be
helped as follows:
Figure 66: Bleed screw location.
1.
Open and remove the bleed screw on the front of the pump. Normally
a small amount of water comes out when it is removed.
2.
Insert a flat blade screwdriver and turn it in the direction of rotation of
the pump (clockwise).
3.
Reinstall the bleed screw with its rubber seal.
28
ENGLISH
Adaptation to the heating system
Adjust the heat pump settings to the applicable heating system,
for instance an underfloor heating or radiator system. The delta
temperature must be at least 8°C above the heat pump. The delta
temperature should be 3-5°C for the brine system. (The flow rate
of the circulation pumps may need to be adjusted depending on
the applicable heating system)
Noise check
During transportation and installation there is a certain risk that
the heat pump can be damaged, components may move or get
bent and this can cause noise. Because of this it is important to
check the heat pump when it has been installed and is ready to
be commissioned to ensure that everything seems in order. The
heat pump should be run in both heating and hot water modes to
ensure that there is no abnormal noise. While doing this, check
that there is no abnormal noise in other parts of the house.
Noise is produced from the outdoor unit when the fan is in
operation, check during that manual operation that there is no
disturbance in your own home as well as to any neighbours. A
noise kit is available for purchase for the outdoor unit for Geysir Air
10 and 12 if it is necessary to reduce the noise.
Select operating mode
Set the heat pump to the desired operating mode in the menu
INFORMATION -> OPERAT. If necessary, set certain parameters
in the control computer, such as ROOM and CURVE.
10.4. INSTALLING THE FRONT COvER
!
NOTE! Take care not to damage the front cover!
1.
Align the upper section of the front cover with both the side
channels at the top of the unit and slide it carefully downwards
until it covers the entire front of the unit.
2.
Tighten the screws.

10.5. AFTER START UP

!
NOTE! Remember that it takes time for the heat pump
to heat a cold house. It is best to let the heat pump
work at its own pace and NOT raise any values in the
control computer to try to heat it up more rapidly.
!
NOTE! If there is an LP alarm in conjunction with
installation it usually means that there is air in the
system. Normally the alarm disappears after a few
days. If the alarm does not stop the brine circuit must
be bled and topped up.