WARNING:
•
The leveling jacks are extended to the floor.
The full weight of the rack rests on the leveling jacks.
•
The stabilizing feet are attached to the rack if it is a single-rack installation.
•
•
The racks are coupled together in multiple-rack installations.
Only one component is extended at a time. A rack may become unstable if more than one
•
component is extended for any reason.
WARNING:
•
At least two people are needed to safely unload the rack from the pallet. An empty 42U rack
can weigh as much as 115 kg (253 lb), can stand more than 2.1 m (7 ft) tall, and might
become unstable when being moved on its casters.
Never stand in front of the rack when it is rolling down the ramp from the pallet. Always handle
•
the rack from both sides.
Identifying the contents of the server shipping carton
Unpack the server shipping carton and locate the materials and documentation necessary for installing the
server. All the rack mounting hardware necessary for installing the server into the rack is included with the
rack or the server.
The contents of the server shipping carton include:
•
Server
•
Power cord
•
Hardware documentation and software products
•
Rack-mounting hardware and documentation
In addition to the supplied items, you might need:
•
Operating system or application software
•
Hardware options
•
Screwdriver
Installing hardware options
Install any hardware options before initializing the server. For options installation information, refer to the
option documentation. For server-specific information, refer to "Hardware options installation (on page 32)."
Installing the server into the rack
To install the server into a rack with square, round, or threaded holes, refer to the instructions that ship with
the rack hardware kit.
If you are installing the server into a telco rack, order the appropriate option kit at the RackSolutions.com
website (http://www.racksolutions.com/hp). Follow the server-specific instructions on the website to install
the rack brackets.
Use the following information when connecting peripheral cables and power cords to the server.
To reduce the risk of personal injury or damage to the equipment, be sure that:
To reduce the risk of personal injury or equipment damage when unloading a rack:
Setup 28