7  Commissioning
Example: from 10:00 p.m. to 6:00 a.m., the load-shedding contactor is not to disconnect
loads from the stand-alone grid where possible.
Figure 25: Profile of the SOC limiting values for controlling the load-shedding contactor and the start times for
the intervals
The start time for the first interval is set to 6:00 a.m. The lower SOC limiting value is set to 40% and
the upper SOC limiting value is set to 80% in this time interval.
The start time for the second interval is set to 10:00 p.m. The lower SOC limiting value is set to 30%
and the upper SOC limiting value is set to 40% in this time interval.
Requirement:
☐ In a cluster, the Sunny Remote Control must be connected to the master.
1. Switch to installer mode (see Section 7.5).
2. Select the 242.05 Lod1Tm1Str parameter and set it to the start time for the first interval.
3. Select the 242.06 Lod1Tm2Str parameter and set it to the start time for the second interval.
4. Select the 242.01 Lod1SocTm1Str parameter and set it to the lower SOC limiting value for
the first interval.
5. Select the 242.02 Lod1SocTm1Stp parameter and set it to the upper SOC limiting value for
the first interval.
6. Select the 242.03 Lod1SocTm2Str parameter and set it to the lower SOC limiting value for
the second interval.
7. Select the 242.04 Lod1SocTm2Stp parameter and set it to the upper SOC limiting value for
the second interval.
8. Ensure that the multi-function relay used for control is set to AutoLod1Soc (see Section 7.10.2).
94
SI80H-60H-OffGrid-IA-en-11
SMA Solar Technology AG
Installation Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sunny island 6.0h

Table of Contents