Example: from 10:00 p.m. to 6:00 a.m., the generator is not to start where possible.
Figure 28: Profile of the SOC and the times for generator requests
The start time for the first interval is set to 6:00 a.m. In the first interval, the lower SOC limiting value
is set to 40% and the upper SOC limiting value is set to 80%.
The start time for the second interval is set to 10:00 p.m. In the second interval, the lower SOC
limiting value is set to 30% and the upper SOC limiting value is set to 40%.
1. Switch to installer mode (see Section 7.5).
2. Select the 235.07 GnTm1Str parameter and set it to the start time for the first interval.
3. Select the 235.03 GnSocTm1Str parameter and set it to the lower SOC limiting value during
the first interval.
4. Select the 235.04 GnSocTm1Stp parameter and set it to the upper SOC limiting value during
the first interval.
5. Select the 235.08 GnTm2Str parameter and set it to the start time for the second interval.
6. Select the 235.05 GnSocTm2Str parameter and set it to the lower SOC limiting value during
the second interval.
7. Select the 235.06 GnSocTm2Stp parameter and set it to the upper SOC limiting value during
the second interval.
108
SI80H-60H-OffGrid-IA-en-11
SMA Solar Technology AG
Installation Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sunny island 6.0h

Table of Contents