INSTALLATION PROCEDURE

1.2 INSTALLATION PROCEDURE
CAUTION
Always switch the machine off and unplug the machine before doing any of
the following procedures.
1.2.1 BEFORE YOU BEGIN
• Do the installation procedure for the finisher but do not dock it to the machine.
The Z-folding unit must be installed between the finisher and the main machine.
• Do the installation for the cover sheet feeder (if necessary).
• If the finisher is already installed, disconnect the finisher from the main machine.
(If the cover sheet feeder is installed on the finisher, it is not necessary to remove
the cover sheet feeder.)
IMPORTANT NOTES:
1. To install the Z-Folding Unit (B660) on the
enhanced version of the B070/B071 mainframe,
it is necessary to first install the new 3000 Sheet
Finisher (B706).
2. To install the Z-Folding Unit (B660) unit on
existing B070/B071 machines it will be necessary
to update to the latest firmware version. These
details will be announced as soon as they
become available.

1.2.2 UNPACKING

This installation procedure uses the
following symbols.
1. Detach the I/F connector [A].
2. Remove all tape from unit.
3. Open the front door [B].
4. Raise the horizontal transport plate [C].
5. Pull out the Z-folding mechanism [D].
6. Remove all tape and shipping material.
B660
CÓPIA NÃO CONTROLADA
: Screws
CÓPIA NÃO CONTROLADA
[C]
[D]
2
[A]
[B]
B660I002.WMF