Chapter 2
Each cabinet of your UPS system is shipped on a separate pallet. Use a forklift or pallet jack
to move the packaged cabinets to the installation site, or as close as possible to the site,
before you unload them from the pallets.
This is the basic sequence of the installation steps:
After wiring the UPS system to the facility power and critical load(s), be sure to ground the
system according to local and/or national electrical wiring codes, using your own cabling
and conduit.
Install batteries in accordance with all applicable codes and regulations, including the
National Electrical Code (NEC) Article 480.
9315 UPS (300–500 kVA) Installation Manual S 164201118 Rev H www.powerware.com
EATON Powerware
®

Getting Started

1. Prepare your site for the UPS cabinet (Chapter 2).
2. Inspect, unpack, and unload the UPS cabinets (Chapter 2).
3. Create an installation plan for the UPS and optional cabinets (Chapter 3).
4. Wire the cabinets together (Chapters 4 through 11, as applicable).
5. Install features, accessories, and/or options (Chapters 4 through 11, as applicable).
6. Complete the Installation Checklist (Chapter 3).
7. Have authorized service personnel perform preliminary checks and startup.
NOTE Startup and operational checks should be performed only by authorized service
personnel. This service is usually offered as part of the sales contract for your UPS
system.