Connect the scale to AC
power. Install the power cable
and grounding cable with
adequate protection so that
they cannot be damaged.
Operating the Scale
Turn on the scale using the e
key (2).
4
Remove the load plate.
Use a 13-mm open-end wrench
to loosen the leveling foot (1).
Turn the leveling foot (2) until
the scale is level. Tighten the
lock nut (1) with the wrench.
Replace the load plate
After connecting the scale to AC power, wait approx. 30 minutes
for it to warm up.
After the scale has been turned
on, it will automatically run a
self-test. At the end of this test,
0.0 g is displayed.
Ground the scale in the
hazardous area/location.
Connect an equipotential
bonding conductor to the
terminal (11).
If a different readout is
displayed, zero or tare the
scale using the = key (4).