Chapter 6
Figure
6.1
Installing a Powerware Hot Sync CAN Bridge Card
Eaton 9390 UPS (100–160 kVA) Installation and Operation Manual
Installing Optional Accessories
This chapter contains installation instructions for the following options:
S
Powerware Hot Sync CAN Bridge Card and parallel system control wiring
S
Remote Monitor Panel (RMP)
S
Relay Interface Module (RIM)
S
Supervisory Contact Module (SCM)
As an option, a Powerware Hot Sync CAN Bridge Card shown in Figure 6‐1, can be
installed to provide connectivity for operational mode control and metering of a
parallel system at any uninterruptible power module (UPM) in the system. In addition,
this card can be used to connect optional system monitoring devices, such as an
RMP, RIM, or a SCM to the UPS.
Figure 6‐1. Powerware Hot Sync CAN Bridge Card
NOTE Only one Powerware Hot Sync CAN Bridge Card can be installed in the UPS. Multiple CAN cards are
not supported and will cause system conflicts.
To install a Powerware Hot Sync CAN Bridge Card:
1.
Verify the UPS system is turned off and all power sources are removed. See
Chapter 9, "UPS Operating Instructions," for shutdown instructions.
2.
If not already open, unfasten the front door latch and swing the door open.
3.
Install the Powerware Hot Sync CAN Bridge Card into an open X-Slot
communication bay on the front of the UPS.
Remove the X-Slot cover. See Drawing 164201604-8 starting on page A-33 for
location of the X-Slot communication bay.
S
164201604 Rev E www.eaton.com/powerquality
Plug-in Terminal Block J3