www.ti.com
4.2.7 Control On With Prebiased Output
Figure 4-8
illustrates the control on waveform with a prebiased output voltage.
4.2.8 Thermal Image
Figure 4-9
shows the TPS546C25EVM-1PH thermal image.
V
= 12V, V
= 1.2V, I
IN
OUT
OUT
SLUUCZ1 – JULY 2024
Submit Document Feedback
Figure 4-8. Start-Up From Control With Prebiased Output
= 35A
Figure 4-9. Thermal Image
Copyright © 2024 Texas Instruments Incorporated
TPS546C25EVM-1PH 4V to 18V, 35A, Buck Converter with PMBus and
Implementation Results