● Wrench an anchor bolt clockwise to elevate the cabinet, or wrench it
counterclockwise to lower the cabinet. The anchor bolts can be wrenched
within a range of 0–8 mm.
● To prevent cabinet tilting, adjust the four anchor bolts instead of one anchor
bolt.
● Use a measuring tape for measurement when leveling the cabinet to ensure
that the height between the cabinet top and the floor is 2000 mm (tolerance
+3 mm).
● Do not remove anchor bolts. Otherwise, you need to rework them for use.
Step 3 Insert four M12 bolt assemblies into the mounting holes on the UPS and support,
and tighten the bolts.
Figure 4-12 Leveling and tightening bolts
(1) Anchor bolt
----End

4.2.2 Installing a Tail Frame

Issue 05 (2024-01-30)
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
(2) Fixing bolt
(3) Level
72

Advertisement

Table of Contents
loading

Table of Contents