DRAINING THE COOLING SYSTEM

GB
In order to carry out maintenance on the water/air
Genset
exchanger or the cooling system, the seawater
intake circuit must be drained.
2
Carry out this operation as follows:
1
- Close the seawater intake cock (ref.1).
Discarge
- Open the drain tap (ref.2) until all the water has
drained out.
- Close the drain tap.
3
Sea Water
Reopen the seawater intake cock before starting the
generator.
6.10 R
EPLACING THE ZINC ANODE
A sacrificial zinc anode (ref. 3) has been fitted in the
heat exchangers to protect them against galvanic
currents.
Periodically check the state of wear and replace it if
necessary, in order to prevent galvanic currents from
irreparably corroding the exchanger. It is recommended
to check the zinc anode at least once a month when the
generator is new in order to check how fast it wears,
and then act accordingly.
It is in any case advisable to replace the zinc anode at
least once a year.
3
3
GB
- 37

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the IS 6.1 and is the answer not in the manual?

Subscribe to Our Youtube Channel

This manual is also suitable for:

43478

Table of Contents

Save PDF