Connection and commissioning

5.1

Connecting the supply cable

Select the cable cross-section according to load and voltage drop:
NOTE
Three-phase operation
The charging station may only be operated with 3 phases + N + PE. The specifications can be
obtained from the rating plate (Page 17).
• Main line: 10 - 35 mm² rigid/stranded, 3.5 Nm
• Branch line to a second charging station: 1.5 - 25 mm² rigid/stranded, 2.5 Nm
• Stripped length: 25 mm
NOTE
Option: HAK
Cable routing and the procedure for the HAK option are described in section Option: HAK
(Page 98).
Procedure
Risk of electric shock
When connecting the SICHARGE charging station, pay attention to the five safety rules.
With the double terminal option, make sure that the branch line is not unintentionally
energized.
SICHARGE Operating Instructions MID
Operating Instructions, 02/2023, A5E48573001-AF
DANGER
5
37