6.5.12 Sidewall Termination and Fittings

Ensure the following when installing through sidewalls:
The air termination coupling must be oriented at least 12 inches above grade or snow line
as shown in Figure 6-5.
Maintain the required dimensions of the finished termination piping shown in Figure 6-5.
Do not extend exposed vent pipe outside of the building more than what is shown in
Figure 6-5. Condensate could freeze and block vent pipe.

6.5.13 Multiple Vent and Air Terminations

When installing multiple air and vent terminations, ensure the following:
Terminate each vent/air connection as shown in Figure 6-7.
All vent pipes and air inlets must terminate at the same height.
Place wall penetrations to obtain minimum clearance of 12 inches between edge of air
inlet and adjacent vent outlet, as shown in Figure 6-7 for U.S. installations. For Canadian
installations, provide clearances required by CSA B149.1 Installation Code.
The air inlet is part of a direct vent connection. It is not classified as a forced air intake
with regard to spacing from adjacent appliance vents.