Hoist The Cabinet; Remove The Cabinet From The Pallet - ABB Terra HP Generation 3 CE Instruction Manual

175 kw static dc system
Table of Contents

Advertisement

5.5.4

Hoist the cabinet

Preliminary requirements
Procedure
1. Install the swivel eye bolts or bolts
with lifting loops (A).
2. Connect the cables (B) of the hoisting
equipment to the swivel eye bolts or
bolts with lifting loops.
3. Move the cabinet to the correct
location.
4. Remove the swivel eye bolts or bolts
with lifting loops (A).
5. Install the plastic cover on the
threaded location.
5.6

Remove the cabinet from the pallet

Preliminary requirements
9AKK107992A2254-EN | 005
The cabinet is unpacked.
Refer to section 5.4.
Warning:
Risk of pinching or crushing, the cabinet is heavy
Make sure that the hoisting equipment can lift the cabinet safely.
Obey the safety instructions that apply to the hoisting equipment.
Take into account the dimensions, the mass and the center of gravity
of the EVSE. Refer to sections
Caution:
Do not drop the cabinet.
Make sure that there are no dynamic forces on the hoisting points.
Make sure that the weight is equally distributed between the hoisting
points.
Open spanner
Inspection and transport
Hoisting equipment,
including cables (not
chains), swivel eye bolts
or bolts with lifting loops.
Refer to section 12.3.
12.10
and 12.15.
B
A
35

Advertisement

Table of Contents
loading

Table of Contents