11-2. Run-In Procedure Using Load Bank Or Resistance Grid

3
Stop engine.
Do not touch hot exhaust pipe, en-
gine parts, or load bank/grid.
Keep exhaust and pipe away from
flammables.
NOTICE – Do not perform run-in procedure
at less than 20 volts weld output and do not
exceed duty cycle or equipment damage
may occur.
1 Load Bank
Turn all load bank switches Off. If needed,
connect load bank to 115 volts AC wall re-
ceptacle
or
generator
auxiliary
receptacle.
2 Welder/Generator
Place Welder Selector switch in the A posi-
tion (Single Operator) and rotate A/V control
to minimum. Place Process Selector switch
3
in Stick position.
3 Weld Cables
2
1
5
Connect load bank or resistor grid to gener-
ator Side A weld output terminals using
2
proper size weld cables with correct connec-
tors. Observe correct polarity.
1
4 Resistance Grid
Use grid sized for generator rated output.
Turn Off grid.
5 Voltmeter
6 Clamp-On Ammeter
Connect voltmeter and ammeter as shown,
power
if not provided on generator.
Start engine and run for several minutes.
For Load Bank
Set load bank switches and then adjust
generator A/V control so load equals
rated voltage and current of generator
(see nameplate, rating label, or the speci-
fications section in this manual).
5
7
+
3
For Resistance Grid
Set grid switches and then adjust gener-
ator A/V control so load equals rated
voltage and current of the generator (see
nameplate, rating label, or the specifica-
tions section in this manual).
Check generator and meters after first five
minutes then every fifteen minutes to be
sure generator is loaded properly.
NOTICE – Check oil level frequently during
7
run-in; add oil if needed.
It is recommended to run the welder/genera-
tor for two hours minimum and up to four
hours under load. Place A/V control in mini-
mum position, then shut down load bank or
grid to remove load. Run engine several mi-
nutes at no load.
7 Engine Exhaust Pipe
Repeat procedure if wetstacking is present.
+
2
6
Stop engine and let cool.
6