Installation Procedures - All Deployments
11
10
Figure 1: Overview of the MSA1500 cs installation procedures
Note:
including:
Locate the heaviest items, such as Uninterruptable Power Supplies (UPS) near the
bottom of the rack.
Rack some of the storage enclosures above the MSA1500 cs and some of the
storage enclosures below the MSA1500 cs.
16
1
2
7
3
4
5
9
When installing items in your rack, follow industry-standard recommendations,
8
~A
~B
~A
~B
6
Modular Smart Array 1500 cs Installation Guide
1 Review your plans
2 Prepare your site
3 Install MSA1500 cs option kits
4 Rack your MSA1500 cs
5 Rack your storage enclosures
6 Prepare your servers
7 Install the HBAs
8 Prepare your switches
9 Connect your cables
Power on your components
Configure your MSA1500 cs
;
Need help?
Do you have a question about the StorageWorks Modular Smart Array 1500 cs and is the answer not in the manual?