Preparing for use
4.5 Transporting the charging station
To transport the charging station to the installation site with a crane, proceed as follows:
1. Remove the cover on the top by loosening the 9 screws and removing the cover plate.
2. Remove the plate by loosening the 4 screws.
3. Mount the two supplied rails and fix them to the outer holes with two screws each.
4. Hook the hoisting gear into the crane lugs.
5. Lift the charging station vertically.
6. Transport the charging station hanging upright to the site.
7. Remove the two rails and mount the cover plate.