Safety Guidelines

Adherence to the following will aid in problem-free installation with
Installation
long-term reliability:
Precautions
• All components, circuits, system operations, or software functions
• This system meets NFPA requirements for operation at 0-49ºC and at a
All manuals and user guides at all-guides.com
!
WARNING:
Several different sources of power can be
connected to this Fire Alarm Control Panel
(FACP). Disconnect all sources of power before
servicing. Control unit and associated equipment
may be damaged by removing and/or inserting
cards, modules, or interconnecting cables while the
unit is energized. Do not attempt to install, service,
or operate this unit until this manual is read and
understood.
!
CAUTION: System Reacceptance Test after Software Changes:
To ensure proper system operation, this product must
be tested in accordance with the National Fire
Protection Agency (NFPA) NFPA 72-1997
Chapter 7 after any programming operation or change
in site-specific software. Reacceptance testing is
required after any change, addition or deletion of
system components, or after any modification, repair,
or adjustment to system hardware or wiring.
known to be affected by a change must be 100% tested. In addition, to
ensure that other operations are not inadvertently affected, at least 10%
of initiating devices that are not directly affected by the change, up to a
maximum of 50 devices, must also be tested and proper system
operation verified.
relative humidity of 85% RH (non-condensing) @ 30ºC. However, the
useful life of the system's standby batteries and the electronic
components may be adversely affected by extreme temperature ranges
and humidity. Therefore, it is recommended that this system and its
peripherals be installed in an environment with a nominal room
temperature of 60-80ºF.
Hardware Installation—Installing the IFC-1010/2020
N30
5

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the METASYS IFC-1010 and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Metasys ifc-2020

Table of Contents