Johnson Controls IFC-1010 Technical Manual
Johnson Controls IFC-1010 Technical Manual

Johnson Controls IFC-1010 Technical Manual

Hide thumbs Also See for IFC-1010:

Advertisement

Quick Links

• Location of Content Changes
• Related Documentation
© 2000 Johnson Controls, Inc.
Code No. LIT-448155
Installing the IFC-1010/2020
*Indicates those sections where changes have occurred since the last printing.
IFC-1010/2020 Technical Manual 448
Hardware Installation Section
Technical Bulletin
Issue Date 0500
Page
www.johsoncontrols.com
5
5
7
8
9
9
9
9
11
13
13
*13
15
15
15
15
16
16
17
19
21
27
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the IFC-1010 and is the answer not in the manual?

Questions and answers

Summary of Contents for Johnson Controls IFC-1010

  • Page 1: Table Of Contents

    IFC-1010/2020 Technical Manual 448 Hardware Installation Section Technical Bulletin Issue Date 0500 Installing the IFC-1010/2020 Safety Guidelines Page • Installation Precautions • Fire Alarm System Limitations • FCC Warning Introduction • Location of Content Changes • Supported Products • Capabilities and Capacities •...
  • Page 2 • Monitor Modules • Control Module • Installation • Smoke Detector Installation • XP Series Transponder *Indicates those sections where changes have occurred since the last printing. *Indicates those sections where changes have occurred since the last printing. Hardware Installation—Installing the IFC-1010/2020...
  • Page 3 • NFPA 72-1999 Proprietary Fire Alarm Systems *129 • Fire Alarm and Trouble Signal Transmission *131 • Applying/ Removing Power to the Fire Alarm System Application and Clarification Notes *133 *Indicates those sections where changes have occurred since the last printing. Hardware Installation—Installing the IFC-1010/2020...
  • Page 4 Hardware Installation—Installing the IFC-1010/2020...
  • Page 5: Safety Guidelines

    Therefore, it is recommended that this system and its peripherals be installed in an environment with a nominal room temperature of 60-80ºF. Hardware Installation—Installing the IFC-1010/2020...
  • Page 6 • Follow the instructions in the installation, operating, and programming manuals. These instructions must be followed to avoid damage to the control panel and associated equipment. FACP operation and reliability depend upon proper installation. Hardware Installation—Installing the IFC-1010/2020...
  • Page 7: Fire Alarm System Limitations

    • Equipment used in the system may not be technically compatible with the control. It is essential to use only equipment listed for service with your control panel. Hardware Installation—Installing the IFC-1010/2020...
  • Page 8: Fcc Warning

    Le Present apparell numerique n’emet pas de bruits radioelectriques Requirements depassant les limites applicables aux appareils numeriques de la classe A prescrites dans le Reglement sur le brouillage radioelectrique edicte par le ministere des Communications du Canada. Hardware Installation—Installing the IFC-1010/2020...
  • Page 9: Introduction

    • NAM-232 • LIB-200A • LIB-400 • SIB-2048A Also, the AVPS-24 and AVPS-24E have been replaced by the APS-6R. The IFC-1010/2020 is an Intelligent Analog Addressable Combination Capabilities Fire Alarm/Security Control Panel capable of supporting the following: and Capacities Intelligent Photoelectric, ionization, and thermal (heat) detectors.
  • Page 10 Audio power is provided by several sizes of audio amplifiers for use in Power voice alarm applications. Peripherals An IFC-1010/2020 system can support remotely mounted video display units, printers, and serial annunciators. IFC-2020 IFC-2020 maximum addressable device capacity (ten LIB-200 modules): Maximum 990 Intelligent photoelectric, ionization, and thermal (heat) detectors.
  • Page 11: Fire Alarm And Related Service Standards

    Systems • UL 1481 Power Supplies for Fire Protective Signaling Systems • UL 1638 Visual Signaling Appliances • CAN/ULC - S524 - M91 Standard for Installation of Fire Alarm Systems • Local and state building codes Hardware Installation—Installing the IFC-1010/2020...
  • Page 12 Hardware Installation—Installing the IFC-1010/2020...
  • Page 13: Installation Overview

    BE-2020 and the basic equipment package for the Johnson Controls Equipment IFC-1010 is the BE-1010. The following list may be used to identify various components in a received BE-2020 and/or BE-1010 shipment. Refer to Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160) for an optional equipment listing.
  • Page 14 Hardware Installation—Installing the IFC-1010/2020...
  • Page 15: Cabinet And Component Installation

    Installation The cabinet assembly consists of two basic components; the backbox General (SBB) and door (DR). All cabinets for the IFC-1010/2020 are fabricated from 16-gauge steel. Cabinet parts are painted gray or red with navy blue windows. Provided with the key-locked door are a pin-type hinge, window, two keys, and the necessary hardware to mount the door to the backbox.
  • Page 16: Left Mount

    66 inches above the surface of the finished floor. This procedure places the center of the control panel keypad 60 inches above the finished floor. Cabinet Mounting Holes backmnt Figure 2: Cabinet Backbox Mount Hardware Installation—Installing the IFC-1010/2020...
  • Page 17: Door Assembly Instructions

    Thread remaining stud (B) into the top hinge and through the hole in the top of the door. The door should now swing freely. Top Left Corner Small Hole Faces Outward doorasy1 Figure 3: Door Assembly–Top Left Corner Hardware Installation—Installing the IFC-1010/2020...
  • Page 18 Note: The installation is the same for the top and the bottom right corner of the backbox. Punch out the knockout for the door lock on the side opposite the hinge and install the lock mechanism as shown in Figure 6. Hardware Installation—Installing the IFC-1010/2020...
  • Page 19: Series Backboxes

    (24.125 in. width by 20.125 in. height). The following replacement parts are available: • DR-A3 door • SBB-A3 backbox 24.00 24.125 16.00 1.625 5.218 2.060 8.625 11.281 20.00 20.125 0.3125 0.3125 diameter diameter 2.250 19.50 2.562 caba3 Figure 7: CAB-A3 Hardware Installation—Installing the IFC-1010/2020...
  • Page 20 (24.125 in. width by 37.250 in. height). The following replacement parts are available: DR-C3 door and SBB-C3 backbox. 24.125 24.00 1.625 5.218 4 .0 16.00 2.060 8.625 28.404 8.625 37.125 8.625 37.250 0.3125 0.3125 diameter diameter 19.50 2.250 cabc3 Figure 9: CAB-C3 Hardware Installation—Installing the IFC-1010/2020...
  • Page 21: Mounting The Ica-4L

    19.50 cabd3 Figure 10: CAB-D3 The IFC-1010/2020 system may use one to three Interconnect Chassis Mounting the Assemblies (ICA), depending on the specific installation requirements. ICA-4L The ICA-4L is a low profile mounting chassis that currently replaces the ICA-4 in all BE-1010 and BE-2020 basic equipment kits.
  • Page 22 Expansion power cable, Part Number 75379, is able to mate properly with the ICA-4L since it consists of a 16-pin plug and a 16-position receptacle (Figure 12). Expansion Power Cable Part Number 75379 16-position 16-position Receptacle Plug cbl75379 Figure 12: Expansion Power Cable, Part Number 75379 Hardware Installation—Installing the IFC-1010/2020...
  • Page 23 8-position receptacle to connect to the main power supply (refer to Figure 14). Power Cable Part Number 75378 Connects To Main Power Supply Top View 16-position Side View Receptacle cable2 Figure 14: Power Cable, Part Number 75378 Hardware Installation—Installing the IFC-1010/2020...
  • Page 24 Although cable, Part Number 75142 consists of a 15-pin plug and a 15-position receptacle (Figure 16), it can still be mated on the 16-pin plug ICA-4L, only Pins 1 through 15 will engage. The 16th pin will remain on the outside of the board receptacle (Figure 17). Hardware Installation—Installing the IFC-1010/2020...
  • Page 25 Part Number 75142 15-position 15-position Receptacle Plug cbl75142 Figure 16: Cable, Part Number 75142 Cable Part Number 75142 15-position Receptacle 16th Pin Front View (Chassis in Cabinet) cablecn Figure 17: Cable, Part Number 75142 Connected to the ICA-4L Hardware Installation—Installing the IFC-1010/2020...
  • Page 26 Note: For installation of system boards in the first level of the ICA-4L, omit Steps 2 and 3. ica4lmnt Figure 18: Mount System Boards to the ICA-4L Chassis Hardware Installation—Installing the IFC-1010/2020...
  • Page 27: Component Placement

    Mounts in any one LIB position or any Mounts in either the left or right position two CHS-4/4L positions. of a CHS-4 by using four PEM studs on the CHS-4 chassis. compplac Figure 19: Component Placement Guidelines Hardware Installation—Installing the IFC-1010/2020...
  • Page 28 Figure 20 depicts the LIB SLC numbering scheme for an IFC-1010 in a CAB-B3 cabinet. If CAB-A3 cabinet is used with LIB-400 modules exclusively, it may house a maximum four loop IFC-1010 system. One or two ICA-4L or ICA-4 chassis are required to mount the LIB modules, depending upon the number and type of LIB modules employed.
  • Page 29 (LIB-200A, or LIB-200) Loop 10 (LIB-400) Loop 7 Loop 8 (LIB-200A, or LIB-200) (LIB-200A, or LIB-200) Loop 9 Loop 10 (LIB-200A, or LIB-200) (LIB-200A, or LIB-200) CHS-4/4L MPS-24A Batteries MPS-24AE libmix2 Figure 21: IFC-2020 LIB SLC Numbering Scheme Hardware Installation—Installing the IFC-1010/2020...
  • Page 30 Figure 22 depicts a CAB-A3 cabinet used with LIB-400 modules exclusively, which means it may house a maximum four loop IFC-1010 system. An ICA-4L or ICA-4 chassis (neither of which is shown in the figure) is required for mounting the LIB-400.
  • Page 31 Figure 23 depicts the IFC-1010 with a combination of LIB-400, LIB-200A, and LIB-200 modules installed in the first and second rows of a CAB-C3 cabinet. Two ICA chassis are required, but are not shown in the figure. The always occupies both addresses (refer to Figure 23) as long as the following measures are taken: •...
  • Page 32 LIB-400. Loop 7 Loop 1 Loop 2 Loop 3 Loop 9 Loop 5 Loop 4 Loop 8 Loop 10 CHS-4/4L Batteries MPS-24A lib400pl ex Figure 24: LIB-400 Placement in an IFC-2020 Hardware Installation—Installing the IFC-1010/2020...
  • Page 33 Loop 7 (LIB-400) Loop 1 (LIB-200A) Loop 2 (LIB-400) Loop 3 Loop 4 (LIB-200) Loop 5 (LIB-400) Loop 6 (LIB-200) Loop 8 Loop 10 CHS-4/4L Batteries MPS-24A lib400pl Figure 25: LIB Placement Examples in an IFC-2020 Hardware Installation—Installing the IFC-1010/2020...
  • Page 34 CPU to DIB cable. Only one DIA is required per system. The DIA-2020 is included with the BE-2020 Basic Equipment Package for the IFC-2020. The DIA-1010 is included with the BE-2020 Basic Equipment Package for the IFC-1010. Figure 27 depicts the basic system. Hardware Installation—Installing the IFC-1010/2020...
  • Page 35 The Battery Dress Panel (BP-3) covers the batteries in the cabinet. Only one BP-3 is required per system. DP-1 The Dress Panel (DP-1) covers additional ICA-4L or CHS-4/4L assemblies in the cabinet. ifcpanel Figure 27: Intelligent Fire Detection and Alarm System Hardware Installation—Installing the IFC-1010/2020...
  • Page 36 3 2 1 at the cabinet entrance only. Plug this DB-25 connector into the RS-232 port of N14 N15 the PRN-3 printer, or Keltron Printer No. VS4095/5. diaconn N13, N14, N15, N16, N17 Figure 28: Display Interface Assembly Hardware Installation—Installing the IFC-1010/2020...
  • Page 37 Figure 29: Wiring Placement Diagram Note: The battery charger output is not power-limited. All wiring connected to these terminals must remain at least 6.35 mm (0.25 inch) from all power-limited wiring. Refer to Figure 30. Hardware Installation—Installing the IFC-1010/2020...
  • Page 38 Figure 30 depicts a typical IFC-1010/2020 installation and is provided as a guide for proper wiring placement. The AC and battery wiring are not power-limited. A separation of at least 1/4 inch must be maintained between power-limited and non power-limited wiring. Install the tie wraps and adhesive squares as indicated in Figure 30.
  • Page 39 Several Different Sources of Power can be Connected to this Control Unit. Disconnect all Sources of Power Before Servicing. Ground Fault Ground Fault Battery Fail AC Power Fail panelplc BP-3 Battery Dress Panel Figure 31 : Dress Panel Placement Diagram Hardware Installation—Installing the IFC-1010/2020...
  • Page 40 Hardware Installation—Installing the IFC-1010/2020...
  • Page 41 Power Supplies The IFC-1010/2020 requires connection to a separate dedicated AC fire AC Primary alarm circuit, which must be labeled FIRE ALARM. This AC circuit Power Input must connect to the line side of the main light and power feed of the protected premises.
  • Page 42 The following paragraphs provide additional information to the IFC-1010/2020 System Current Draw Calculation table (Table 5). • In the IFC-1010/2020 System Current Draw Calculation table (Table 5), the primary power non-fire alarm current and the primary fire alarm current columns are not battery calculations. They are...
  • Page 43 MPS-24A or MPS-24AE during a fire alarm. • No more than 3.0 amperes of current can be drawn from Terminals 3 and 4 of TB3. • Security Alarms are treated as trouble (non-fire alarm) conditions in the IFC-1010/2020. Hardware Installation—Installing the IFC-1010/2020...
  • Page 44 Table 5: IFC-1010/2020 System Current Draw Calculations Category Primary, Non-Fire Alarm Primary, Fire Alarm Secondary, Non-Fire Current (amperes)* Current (amperes) Alarm Current (amperes) X Current Total X [Current Total X Current Total Draw] = Draw] = Draw] = BE-2020 or x [0.162] =...
  • Page 45 [0.016] = ACM-32A x [0.016] = x [0.016] = AEM-16AT AEM-32A x [0.016] = x [0.016] = Primary, Non Alarm Primary, Alarm Secondary, Alarm Sum Each Column for Subtotals Continued on next page . . . Hardware Installation—Installing the IFC-1010/2020...
  • Page 46 ATG-2 FFT-7 x [0.060] = x [0.120] = x [0.060] = x [0.060] = x [0.120] = x [0.060] = FFT-7S XP5-M x [0.00165] x [0.0030] = x [0.00165] Continued on next page . . . Hardware Installation—Installing the IFC-1010/2020...
  • Page 47 [ ] = power from MPS-24A Terminals TB3- 3 and TB3-4 Primary, Non Alarm Primary, Alarm Secondary, Alarm Sum Each Column for Totals * MPS-24A or MPS-24E output current required when operating from primary power. Hardware Installation—Installing the IFC-1010/2020...
  • Page 48 AA-30 or AA-30E AA-100 or AA-100E AA-120 or AA-120E Amperes Sum Column for Secondary Fire Alarm Load* = * The secondary fire alarm load cannot exceed 9.0 amperes with PS-12250 batteries, and 20 amperes with PS-12550 batteries. Hardware Installation—Installing the IFC-1010/2020...
  • Page 49 Total Secondary Ampere Hours Required Table 8 sums the non-fire alarm and alarm loads to arrive at the battery size in Ampere-Hours (AH), required to support the IFC-1010/2020. The MPS-24A or MPS-24AE can charge batteries up to 60 AH in size.
  • Page 50 We need 1.25 amperes for 20 hours. Using Ohm’s Law, R=E/I, therefore, R=12/1.25, or 9.6 ohms. P=I x E, so P=1.25 x 12, or 15 watts. Therefore we need a load resistor of 9.6 ohms at 15 watts. Hardware Installation—Installing the IFC-1010/2020...
  • Page 51 Figure 32: Mount the Main Power Supply Hardware Installation—Installing the IFC-1010/2020...
  • Page 52 1. Remove the upper and lower screws on the right side of the power supply main board. 2. The MPS-TR mounts on these two holes. Thread the new longer screws and the standoff sleeves into the holes formerly occupied by the two screws removed in Step 1. Hardware Installation—Installing the IFC-1010/2020...
  • Page 53 Screw MPS-TR MPS Series Power Supply Board (MPS-24A Shown) In Remote Location Nylon standoff does not MPS-24 screw into MPS-24A main power MPS-24B supply board, but rests on it. Mounting Hole Figure 34: Mounting the MPS-TR Hardware Installation—Installing the IFC-1010/2020...
  • Page 54 MPS-24B MPS-24B TB2-4 Syscomm Figure 35: System Common Terminal Connection Note: Relay contacts are specified in the NORMAL (no trouble condition) state. The MPS-TR connects to any device with a trouble IN and a trouble OUT. Hardware Installation—Installing the IFC-1010/2020...
  • Page 55 JP5 on the MPS-24A or MPS-24AE (refer to Figure 36). This 24 VDC power is power-limited but must be supervised via an end-of-line power supervision relay. Hardware Installation—Installing the IFC-1010/2020...
  • Page 56 NVRAMS to become inaccessible. The IFC-1010/2020 software now verifies the state of the NVRAMs. If a NVRAM problem has been detected, the IFC-1010/2020 will display one of the following two error messages depending on where the problem is located: TROUBL CATASTROPHIC CPU NONVOLATILE RAM FAILURE...
  • Page 57 Power for any 24 VDC UL-Listed device (typically notification appliances). Connection: TB3 Terminal 3 (+) and 4 (-). Remote Battery JP1 must be cut to install either a NR45-24/E or CCHG-120 remote battery Charger charger and disable the MPS-24A/E internal charger. Hardware Installation—Installing the IFC-1010/2020...
  • Page 58 CHG-120 Remote Battery Charger. Figure 36: Field Wiring the MPS-24A or MPS-24AE Power Supply Table 10: Maximum Loads Alarm Load (amperes) Non-Fire Alarm Fire Alarm For additional ratings, see Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160) in this manual. Hardware Installation—Installing the IFC-1010/2020...
  • Page 59 MPM-2 assembly over the MPS-24A and secure with the two screws. mpminst Step 3 Complete the installation of the MPM-2 by plugging the female connector on the meter into Plug P7 on the MPS-24A or MPS-24AE. Figure 37: Installation of the Main Power Meter Hardware Installation—Installing the IFC-1010/2020...
  • Page 60 Hot line to Terminal 1 on the NR45-24 and the primary Primary Power Neutral line to Terminal 2. All connections between the IFC-1010/2020 Source and the NR45-24 must be made in conduit, using 12 AWG wire. Do not route AC wiring in the same conduit as other control panel circuits.
  • Page 61 Primary Power the primary power source to the corresponding terminal on TB1 of the Source CHG-120. All connections between IFC-1010/2020 and the CHG-120 must be made in conduit, using 12 AWG (3.25 mm ) wire. Do not route AC wiring in the same conduit as other control panel circuits. Leave the main power breaker off until installation of the entire system is complete.
  • Page 62 – – 55 AH/ 55 AH/ 60 AH 60 AH (12 V) (12 V) Battery Interconnect Cable – – 55 AH/ 55 AH/ 60 AH 60 AH (12 V) (12 V) chgbatcx Figure 40: CHG-120 Connections Hardware Installation—Installing the IFC-1010/2020...
  • Page 63 Be sure that the input voltage specified for the main power supply (MPS-24A or MPS-24AE) matches the required input voltage for the AVPS-24 or AVPS-24E selected, i.e., both supplies must be 120 VAC input or both supplies must be 220/240 VAC input. Hardware Installation—Installing the IFC-1010/2020...
  • Page 64 The APS-6R Auxiliary Power Supply is designed to power devices that APS-6R require filtered, non-resettable power such as XP Transponder modules, Auxiliary notification appliance circuit modules, and control modules. It provides Power Supply two 24 VDC (filtered) output circuits (3A each, 6A total, 4A continuous). Hardware Installation—Installing the IFC-1010/2020...
  • Page 65 Mount the CHS-4 or CHS-4L to the cabinet backbox. Install the APS-6R plastic cover and press-fit terminal block cover over TB1 AC connections. Mounting Stud CHS-4L Chassis APS-6R Standoffs CHS-4 Chassis APS-6R Standoffs chsmnt_aps6r Figure 42: Mounting the APS-6R to a Chassis Hardware Installation—Installing the IFC-1010/2020...
  • Page 66 To reduce the risk of electric shock make sure to properly ground the APS-6R. Press-fit terminal block cover for TB1 AC connections. Install when finished connecting AC power. Plastic Cover APS-6R wcov Figure 43: Cover Installations Hardware Installation—Installing the IFC-1010/2020...
  • Page 67 J3 and J4. Power Supplies Notes: 1. Use Cable 71033 or 75098 (same cables, different lengths) for all wiring. 2. APS-6R J3 and J4 and AVPS-24 P1 and P2 can be interchanged. Hardware Installation—Installing the IFC-1010/2020...
  • Page 68 To trouble input on control panel: IFC-2020 CPU-2020 P5, IFC-1010 CPU-2 P5, XPP-1 P6. Cable 71033/75098 Cable 71033/75098 Cable 71033/75098 To AVPS-24 or AVPS-24E, CCM-1, AMG-1, or another APS-6R if these devices are employed. Aps6rbus Figure 45: Trouble Bus Connections for Multiple APS-6R...
  • Page 69 Note: Contacts may be connected to power-limited or non power-limited sources of power. Refer to the power-limited information label located inside the door of the FACP. All circuits that are connected to non power-limited sources of power must be identified on this label. Hardware Installation—Installing the IFC-1010/2020...
  • Page 70 Hardware Installation—Installing the IFC-1010/2020...
  • Page 71 99 intelligent detectors, and an additional combination of up to Signaling Line 99 addressable pull stations, and control and monitor modules. Circuit The IFC-2020 supports up to ten LIB-200 boards, the IFC-1010 supports up to two boards. Hardware Installation—Installing the IFC-1010/2020...
  • Page 72 DCLA, and Style 7 to a DCLR. If you are experiencing excessive noise on speaker or phone circuits in the IFC-1010/2020, the LIB-200 SLC polling signal may be the source. To reduce noise, connect the SLC shields to main panel power supply system common of the MPS-24A, TB3, Terminal 6, or use a LIB-200A/LIB-400.
  • Page 73 CPU failure. The LIB-400 has two LEDs per loop; yellow indicates an earth fault and red indicates an alarm condition during local mode only (refer to Figure 48). Hardware Installation—Installing the IFC-1010/2020...
  • Page 74 SLC Loop Port B+ SLC Loop Port B- Connect to Earth Ground Using Supplied Cable LIB-400 libs Figure 48: Loop Interface Boards Note: Only one earth ground connection is required on the LIB-400 at either TB1 or TB2. Hardware Installation—Installing the IFC-1010/2020...
  • Page 75 Branch A Branch B Branch C Branch D + Branch E 3,048 m (10,000 feet) or less LIB-200A or LIB-400: Branch A Branch B Branch C Branch D + Branch E 3,810 m (12,500 feet) or less Hardware Installation—Installing the IFC-1010/2020...
  • Page 76 The total of all branches on Channel A: LIB-200 must be less than or equal to 10,000 feet and LIB-200A/LIB-400 must be less than or equal to 12,500 feet. slcstyl4 Figure 49: SLC Loop Wiring Requirements (Style 4) Hardware Installation—Installing the IFC-1010/2020...
  • Page 77 Channels A and B at the control panel, shorting the two leads at the input of Channel A, and metering the two leads of Channel B. Channel B Channel A slcstyl6 Figure 50: SLC Loop Wiring Requirements (Style 6) Hardware Installation—Installing the IFC-1010/2020...
  • Page 78 No Connection Channel A (+) Note: Refer to Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160) and installation drawings supplied with each loop device for rating and specification information. nfpastl4 Figure 51: Typical NFPA Style 4 SLC Loops Hardware Installation—Installing the IFC-1010/2020...
  • Page 79 No Connection Channel A (+) Note: Refer to Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160) and installation drawings supplied with each loop device for rating and specification information. nfpaslc6 Figure 52: NFPA Style 6 LIB SLC Loop Hardware Installation—Installing the IFC-1010/2020...
  • Page 80 The circuit illustrated in Figure 53 is a variation of an NFPA Style 6 SLC, in this case, no T-tapping or branching is allowed. The rating and characteristics are the same as for the Style 6 circuit. Hardware Installation—Installing the IFC-1010/2020...
  • Page 81 LIB-200 SLC Loop Figure 53: NFPA Style 7 SLC Note: When more than 100 isolator modules/isolator bases are connected to an SLC, decrease the 198 address capacity by two address for every isolator in excess of 100. Hardware Installation—Installing the IFC-1010/2020...
  • Page 82 SLC loop from short circuit faults on other branches or sections of the loop. SLC Loop In (-) SLC Loop In (+) SLC Loop Out (-) SLC Loop Out (+) M500XJ m500xj1 Figure 55: Loop Isolator Module (M500XJ) Hardware Installation—Installing the IFC-1010/2020...
  • Page 83 Shorts on the remainder of this NFPA Loop Style 4 SLC loop will be isolated from M500XJ all devices installed upstream of the M500XJ. Remainder of the SLC Loop xj4slc2 Figure 57: Isolating the Remainder of a Style 4 SLC Loop Hardware Installation—Installing the IFC-1010/2020...
  • Page 84 This circuit cannot be T-tapped or branched in any fashion. No external EOLR is required for Style D wiring. Connect the four wire circuit to M500MJ Terminals 6 and 9 (-), then 7 and 8 (+). Hardware Installation—Installing the IFC-1010/2020...
  • Page 85 ADDRESS LOOP IDC (-) IDC (+) SLC (+) SLC (-) (White) (Violet) (Red) (Black) NFPA Style B Initiating Device Circuit Terminate with an End-of-Line Resistor 47K,1/2 watt (A2143-20) m501mj Figure 59: M501MJ Monitor Module Hardware Installation—Installing the IFC-1010/2020...
  • Page 86 Figure 60: NFPA Style B Initiating Device Circuit Note: A SLC control point (M510CJ or XPR-8) with a Type ID or PWRC is necessary to control power to the detectors to execute a system reset when using the APS-6R. (see Figure 62). Hardware Installation—Installing the IFC-1010/2020...
  • Page 87 Figure 61: NFPA Style D Initiating Device Circuit Note: A SLC control point (M510CJ or XPR-8) with a Type ID or PWRC is necessary to control power to the detectors to execute a system reset when using the APS-6R. (see Figure 62). Hardware Installation—Installing the IFC-1010/2020...
  • Page 88 Fire Protective Signaling MPS-24A/E, TB3 Terminal 1 (+) and 2 (-) APS-6R, TB2 Terminal 1 (+) and 2 (-) and Terminal 3 (+) and 4 (-) Figure 62: Employing Four Wire Smoke Detectors (Style B IDC) Hardware Installation—Installing the IFC-1010/2020...
  • Page 89 24V power loop, which must function at the same time in alarm. is the detector current in alarm. is the end-of-line relay current. Hardware Installation—Installing the IFC-1010/2020...
  • Page 90 Power Supply for Fire Protective Signaling MPS-24A/E, TB3 Terminal 1 (+) and 2 (-) APS-6R, TB2 Terminal 1 (+) and 2 (-) Terminal 3 (+) and 4 (-) Figure 63: Employing Four Wire Smoke Detectors (Style D IDC) Hardware Installation—Installing the IFC-1010/2020...
  • Page 91 24V power loop, which must function at the same time in alarm. is the detector current in alarm. is the end-of-line relay current. Hardware Installation—Installing the IFC-1010/2020...
  • Page 92 Figure 65. This power is unsupervised and must be connected to a power supervision relay wired to a M5x0CJ control module (refer to Figure 66 through Figure 68). When a remote power supply is employed, it must also be supervised. Hardware Installation—Installing the IFC-1010/2020...
  • Page 93 Output Circuit 1: 3A @ 24 VDC AVPS-24/E Refer to the Device Compatibility Technical Bulletin (LIT-445180) for compatible devices. 24 VDC 3.0 Amperes (regulated and power-limited) MPS-24A/E APS-6R powmod Figure 65: Providing Power to Control Modules Hardware Installation—Installing the IFC-1010/2020...
  • Page 94 Terminals 3 and 4 of the M5x0CJ and not looped under the terminal hold-down clamp. Any time a power circuit is T-tapped, as seen immediately above the MPS-24A power supply, each branch must end with a Listed power supervision relay. Hardware Installation—Installing the IFC-1010/2020...
  • Page 95 T-tapped, each branch must end a Listed power supervision relay. For connection of the notification appliances, refer to the manufacturer’s installation instructions packed with each device. For device ratings, see Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160). Hardware Installation—Installing the IFC-1010/2020...
  • Page 96 Notes: Each audio/visual power circuit must be supervised by a separate power supervision relay. For connection of the notification appliances, refer to the manufacturer’s installation instructions packaged with each device. For device ratings, see Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160). Hardware Installation—Installing the IFC-1010/2020...
  • Page 97 To next device on SLC Loop M5x0CJ LIB Channel Terminal 3 (-) Terminal 1 (+) Common N.O. Contact N.C. Contact Break off both tabs to enable Form-C operation. cjformc Figure 69: Using the M5x0CJ as a Form-C Relay Hardware Installation—Installing the IFC-1010/2020...
  • Page 98 Addressable The BGX-101L is an addressable manual pull station with a keylock reset Manual Pull feature (refer to Figure 70). Station PUSH IN THEN PULL DOWN pullstn Figure 70: Addressable Manual Pull Station Hardware Installation—Installing the IFC-1010/2020...
  • Page 99 Each pull station must have a unique module address. Refer to Figure 71. Note: During programming of the IFC-1010/2020, this module requires software Type ID MPUL. SLC Loop Out...
  • Page 100 The 5551J (135 degree Fahrenheit fixed temperature) and the 5551JR (rate-of-rise) intelligent thermal sensors takes the temperature and provides it to the control panel. 2551j 1251J The 1251J is a low-profile intelligent ionization smoke detector. 1251j Hardware Installation—Installing the IFC-1010/2020...
  • Page 101 1251J or the 2551J. When sufficient smoke is sensed, an alarm signal is initiated at the control panel. dh500j WARNING: The control panel will only operate with Johnson Controls intelligent addressable devices installed. The B501, B501BJ, B524BI, B524RB, and B501BH provide the Smoke...
  • Page 102 Figure 72: Wiring the Smoke Detector Base Other Intelligent Devices Twisted Pair Recommendation 1-Comm In (+) 2-Comm Out (+) 3-Comm Out (+) 4-Comm In (-) Listed Compatible Control Panel Class A Optional Wiring B52rbi Figure 73: Wiring the B524BI Isolator Base Hardware Installation—Installing the IFC-1010/2020...
  • Page 103 1-Comm In (+) 2-Comm Out (+) 3-Comm Out (+) 4-Comm In (-) 11 Relay Listed Compatible Control Panel 10 Normally Closed 9 Normally Open Class A Optional Wiring b524rb Figure 74: Wiring the B524RB Relay Base Hardware Installation—Installing the IFC-1010/2020...
  • Page 104 B501BJ Base To Next Device on Channel A SLC Loop Maximums: 99 Module Addresses 99 Detector Addresses 40 ohms total loop resistance (LIB-200) 10,000 feet of loop (LIB-200) amslc2 Figure 75: Typical SLC Loop (Style 4) Hardware Installation—Installing the IFC-1010/2020...
  • Page 105 The XP Series Transponder provides the IFC-1010/2020 system with an XP Series efficient multiplex subsystem capability and standalone operation in case Transponder of failure. The XP Transponder communicates directly with the control panel’s CPU along the SLC communications loop. The XP Transponders are extremely effective in both high-rise and...
  • Page 106 Provides eight Form-C relays. The XPR-8 may be configured to provide Module four dual Form-C relays for use in dual channel audio selection applications. (May be power-limited or non power-limited depending on relay connection). Note: For more information, refer to XP Transponder Technical Bulletin (LIT-448180). Hardware Installation—Installing the IFC-1010/2020...
  • Page 107 Serial Communications The IFC-1010/2020 uses serial communication to move data between Optional Serial printers, CRT terminals, and annunciators. The various components used Interface are described here. Boards SIB-2048A The SIB-2048A has two printer and two terminal serial interfaces. The first printer interface supports a PRN Fire Protective Signaling System printer.
  • Page 108 (Solder Cup View) db25 Figure 77: Male DB-25 Connector Shield Wiring to the display monitors, remote annunciators, other peripherals, Terminations and printers must be twisted shielded pairs. Refer to Figure 78 and Figure 79 for pair connections illustrations. Hardware Installation—Installing the IFC-1010/2020...
  • Page 109 Transmit Reference Connect to Pin 1 No Connection DB-25 Connector Pair Connections in Full Conduit IFC-1010/2020 SIB (Shield) (Shield) Reference Transmit Receive Reference No Connection Receive Transmit Reference shieldterm Figure 78: Guidelines for Terminating the Shield Hardware Installation—Installing the IFC-1010/2020...
  • Page 110 Annunciator port (P5 Terminals 5 and 6) are used. SW1 should be placed in the ‘IN’ position if both the primary EIA-485 port and the secondary port (P5 Terminals 3 and 4) are to be used to communicate with annunciator devices. Hardware Installation—Installing the IFC-1010/2020...
  • Page 111 (AUX on first CRT-2 to EIA port on second CRT-2, etc.). Refer to Figure 81 for wiring instructions. Multiple The IFC-1010/2020 will support up to 25 terminals installed on the Terminals EIA-232 circuit of the Serial Interface Board. Each CRT-2 is shipped from the factory with a keyboard.
  • Page 112 CRT Function The function keys on the CRT are labeled with special IFC-1010/2020 Keys commands. These keys function identical to the keys on the DIA. For a description of these commands, refer to the IFC-1010/2020 Operations Technical Bulletin (LIT-448100) in this manual.
  • Page 113 The IFC-1010/2020 can employ PRN-4 Remote Printers. This printer Remote provides a hardcopy printout of all status changes within the system and Printers time stamps the printout with the current time of day and date. The PRN-4 provides 80 columns of data on standard 9 inch by 11 inch tractor-feed paper.
  • Page 114 7 Bit, Even, 1 Stop Format Xon/Xoff Protocol Character Set Standard S1.Zero Auto Line Feed MenLock Paper Bin 1 12/72 12/72 Bin 2 Single 12/72 12/72 Push Tra 12/72 Pull Tra Pap Roll 12/72 Pap Opt Hardware Installation—Installing the IFC-1010/2020...
  • Page 115 EIA-232 port of the printer. Notes: Outputs are power-limited but not supervised. Make connections with overall foil/braided shield twisted pair cable. Near Letter Quality (NLQ) mode cannot be employed on this printer. sibcx Figure 82: Remote Printer to SIB Connections Hardware Installation—Installing the IFC-1010/2020...
  • Page 116 Plug this DB-25 connector into the EIA-232 port of the printer. Main Power Supply TB3-3 (+) Power-limited TB3-4 (-) MPS-24A MPS-24AE DC IN (-) (+) DC IN Keltron Printer Model No. VS4095/5 keltrncx Figure 83: Keltron Printer Connections Hardware Installation—Installing the IFC-1010/2020...
  • Page 117 The Annunciator Expander Module 16AT expands the ACM-16AT by 16 annunciator points. Up to 3 of these expander modules can be supported by an ACM-16AT, to a maximum of 64 annunciator points. acm16 Figure 84: ACM-16AT Hardware Installation—Installing the IFC-1010/2020...
  • Page 118 32 annunciator points. One expander module can be supported by an ACM-32A, providing a maximum of 64 points. For more details on the Annunciator Control System, refer to the ACM-16 and ACM-32 Annunciator Control Modules Technical Bulletin (LIT-445121). Hardware Installation—Installing the IFC-1010/2020...
  • Page 119 Only one expander can be used per SCS-8L. Must be mounted in custom graphic annunciator panel. An SCS annunciator can physically connect to the INA or fire panel, but not both. Hardware Installation—Installing the IFC-1010/2020...
  • Page 120 Refer to Circuit/Device Ratings and Connections Technical Bulletin (LIT-448160) for EIA-485 circuit ratings and limitations. Note: If the SIB is not the first (end) device on the EIA-485 circuit, set SW1 on the SIB to the out position. Hardware Installation—Installing the IFC-1010/2020...
  • Page 121 • NIB-96/AMG-1 power supply remote from the SIB (MPS-24A at TB2-2) • SCS-8/L at TB1-4 • LCD-80 at P1-4 • RPT-485W Reference A at TB1-5 • RPT-485W Reference B at TB2-5 • RPT-485 WF Reference A at TB1-5 Hardware Installation—Installing the IFC-1010/2020...
  • Page 122 Hardware Installation—Installing the IFC-1010/2020...
  • Page 123 Standard-Specific Requirements The IFC-1010/2020 is an expandable multiplex Fire Alarm Control Panel (FACP) designed for use in commercial, industrial, and institutional applications. These panels meet the requirements for service under the National Fire Protection Association (NFPA) and Underwriters Laboratories (UL) Standards outlined in this chapter. The minimum system components required for compliance with the appropriate standard are listed in each section.
  • Page 124 Transmitter - Network Interface Board (NIB-96). • Protected Premise Number Two (refer to Figure 93): The Receiving Unit is an IFC-1010/2020 with an M500MJ or M501MJ Monitor Module for receipt of fire alarms and one M500MJ or M501MJ Monitor Module for receipt of trouble signals from the Protected Premises Unit.
  • Page 125 These outdoor wiring restrictions do not apply to the LIB-200A or the LIB-400. Refer to the Loop Interface Boards (LIB-200, LIB-200 A, and LIB-400) section in this document. Hardware Installation—Installing the IFC-1010/2020...
  • Page 126 Figure 89: Auxiliary Fire Alarm System Note: Wiring between the MBT-1 and the municipal box cannot exceed 1,000 meters (10,000 feet), must not cross any power lines, and must not be in the vicinity of any high voltage. Hardware Installation—Installing the IFC-1010/2020...
  • Page 127 • If individual signal for alarm and trouble are not desired, one control module (M5x0CJ) with one output sounder can be used to indicate both alarm and/or trouble pending. Program this module for software Type ID GPND. Hardware Installation—Installing the IFC-1010/2020...
  • Page 128 Do Not Break Off Tabs! CRT-2 AUX PORT DB-25 Note: When contact state changes, it inhibits answerback. Uninterruptable Power Supply UL Listed for Fire Protective Signaling with normally closed supervisory contacts. uipowsup Figure 91: Uninterruptable Power Supply Hardware Installation—Installing the IFC-1010/2020...
  • Page 129 Slave Reset not used not used A6P4 AMON not used L1M5 A6P5 AMON Security Alarm SARM (typical) L1M6 A6P6 AMON Security Tamper SSYM (typical) L1M7 A6P7 AMON Non-Alarm Input (typical) L1M8 A6P8 ACON Control Output (typical) Hardware Installation—Installing the IFC-1010/2020...
  • Page 130 EIA-485 Loop OUT: conditions. From: NIB-96 P5 Terminals 6 (+) and 4 (-) During programming, NFPA menu option Next device on EIA-485 Loop “72D” must be chosen. propfire Figure 92: Proprietary Fire Alarm Systems Hardware Installation—Installing the IFC-1010/2020...
  • Page 131 MRTB. (N-ELR in Canada) (Contacts shown in their normal state.) M501MJ Programmed with the software Type ID MON. nfpapcsp Figure 93: NFPA 72-1999 Proprietary and Central Station Protected Premises Unit/Proprietary and Central Station Receiving Unit Interface Hardware Installation—Installing the IFC-1010/2020...
  • Page 132 This damage may adversely affect the operation of this control unit but its effect may not be readily apparent. Note: System will not function without power applied. Hardware Installation—Installing the IFC-1010/2020...
  • Page 133 Application and Clarification Notes The IFC-1010/2020 product is listed as a UL Multiple Listing, in association with its original manufacturer. This allows Johnson Controls to provide the latest products, upgrades, and updates available from the manufacturer to the customer at the fastest rate and lowest cost. To conform to this UL Multiple Listing process, this documentation must closely reflect that which is distributed by the product’s original...
  • Page 134 MPS-TR, the charger circuit is not turned off during an alarm condition in the system. NVRAMS, Since the MPS-24A/E is rated for charging 55 AH batteries, it is very unlikely NR45-24 Remote that the NR45-24 would be used. Battery Charger Continued on next page . . . Hardware Installation—Installing the IFC-1010/2020...
  • Page 135 Smoke Detector Power Installation The firmware chips on all of the circuit boards in the IFC-1010/2020 panel Precautions must be part of the same Firmware Group for proper operation of the system. See the Firmware Group file, located in the Library section of the Fire and Security page of The Advisor.
  • Page 136 SLC is no longer installed in conduit), then the SLC shield should be terminated. Controls Group www.johnsoncontrols.com 507 E. Michigan Street FAN 448 P.O. Box 423 IFC-1010/2020 Technical Manual Milwaukee, WI 53201 Printed in U.S.A. Hardware Installation—Installing the IFC-1010/2020...

This manual is also suitable for:

Ifc-2020

Table of Contents