Bottom Cable Routing - Huawei UPS5000-H-600 kVA-FTN Quick Manual

Table of Contents

Advertisement

UPS5000-H-600 kVA-FTN
Quick Guide (Singapore, 100 kVA Power Modules)
Figure 1-35 Installing a signal cable between the UPS and the SmartLi
(1) Monitoring interface unit in the master SmartLi cabinet
----End

1.8.3 Bottom Cable Routing

Procedure
Step 1 Remove the top cover (you do not need to reinstall it later).
Figure 1-36 Removing the cover
Step 2 Remove the bottom cabling cover from the bottom cabling cabinet.
Step 3 Remove the epoxy separators between the top copper bars.
Issue 01 (2022-11-18)
Copyright © Huawei Digital Power Technologies Co., Ltd.
1 Installation and Cable Connection