Huawei UPS5000-H-600 kVA-FTN Quick Manual page 27

Table of Contents

Advertisement

UPS5000-H-600 kVA-FTN
Quick Guide (Singapore, 100 kVA Power Modules)
Figure 1-12 Installing anchor baffle plates
----End
Installation on Channel Steel
● The Company does not provide channel steel or expansion bolts used for
● Ensure that the surface of channel steel is level.
Step 1 Determine the cabinet installation position on the channel steel based on the
mounting holes in the marking-off template or the hole dimensions diagram.
Step 2 Drill mounting holes on the channel steel using a hammer drill.
Step 3 You are advised to use an electric pallet truck to move the cabinet to the
mounting holes on the channel steel.
If the nuts cannot be placed on the side of the channel steel, drill holes near the
mounting holes on the side of the channel steel to place the nuts for securing the
cabinet.
Figure 1-13 Hole positions on the channel steel (optional)
(1) Hole positions on the channel steel
Issue 01 (2022-11-18)
NO TICE
securing channel steel. It is recommended that the customer purchase at least
50 mm wide channel steel.
Copyright © Huawei Digital Power Technologies Co., Ltd.
1 Installation and Cable Connection
21

Advertisement

Table of Contents
loading

Table of Contents