UPS2000-H-(6 kVA–10 kVA)
Quick Guide
2.1 Checking Before Power-On
●
●
●
●
●
●
●
●
●
●
●
●
●
2.2 Lithium Battery
Issue 01 (2022-06-30)
2
AC power cable colors comply with local regulations.
The input and output are not short-circuited.
Cables and terminals are securely connected.
Battery cables and terminals are connected correctly, and voltages comply
with industry standards.
The UPSs are properly connected to battery strings.
Input circuit breakers and load circuit breakers are OFF.
Power cables and signal cables are correctly identified.
The phase sequence of the input power is correct.
Cables are neatly routed and securely bound according to requirements.
Devices are installed and cables are routed in ways that facilitate
modification, capacity expansion, and maintenance.
Parallel cables in a parallel system are properly connected.
Devices are properly grounded.
The voltage range of the UPS upstream input circuit breaker is 80–280 V AC
(phase voltage), and the rated frequency is 50 Hz/60 Hz.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Power-On Commissioning
2 Power-On Commissioning
32