5. Connect the other end of the AC cable to the AC input terminal in the rectifier cabinet, and the wiring is shown in Figure 1.13.
Figure 1.13 AC input cable wiring in rectifier cabinet
Connection without optional AC distribution cabinet
Connect one end of the AC input cable to the user distribution switch outside the power system according to Figure 1.13. Note
2
that the AC input cable should not exceed 150mm
.

1.4.5 Connection of DC load cables

Methods of connecting DC load cables:
1. Choose the length of the cable and wire diameter according to the specific wiring path and load capacity. Obvious color for
distinguishing load positive and negative cables is necessary: positive is brown, negative is blue. If the cables are of the same
color, they should be numbered or identified with insulating tape of different colors at both cable ends.
2. Install naked pressure terminal on both ends of the cable.
3. Select the DC output branch corresponds to load capacity.
Refer to 1.1.2 Cables and Materials Preparation for load output protective components specifications of DC distribution cabinet.
To make the switch works normally, the capacity of the distribution switch should not be less than 1.5 ~ 2 times of the load