Commissioning - WAGNER ZIP52 Translation Of The Original Operating Manual

Pneumatic double diaphragm pump
Table of Contents

Advertisement

Operating manual Pneumatic double diaphragm pump ZIP52 - ZIP80
6   Assembly and Commissioning
2. Crimp the grounding cable on the connection and screw it back onto the pump's foot.
3. Ground the product tank to an on-site grounding connection.
4. Ground the other parts of the system to an on-site grounding connection.
Ex zone
All devices and equipment must be suitable for use in potentially explosive areas.
– All paints, flushing agents and waste tanks have to be electrically conductive.
– All tanks must be grounded.
6.7   COMMISSIONING
WARNING
Gas mixtures can explode if there is an incompletely filled pump!
Danger to life from flying parts.
4 Ensure that the pump and suction system are always completely filled with flushing
agent or working medium.
4 Do not spray the device empty after cleaning.
NOTICE
Impurities in the spraying system
Spray gun blockage, products harden in the spraying system.
4 Flush the spray gun and paint supply with a suitable flushing agent before

commissioning.

Emergency stop, see Chapter Emergency Stop [8 37].
6.7.1   Preparation
Before every commissioning, the following points should be observed as laid down in the
operating manual:
1. Secure spray gun with safety lever.
2. Check the permissible pressures.
3. Check all connections for leaks.
4. Check hoses for damage in accordance with chapter Safety Checks and Maintenance
Intervals [8 42].
6.7.2   Fill the Pump with Flushing Agent
The devices are tested during manufacturing with emulsifying oil, pure oil or solvent.
Possible residues must be flushed out of the circuits with a solvent (flushing agent) before
commissioning.
4 Fill the empty device with flushing agent in accordance with Chapter Filling the Empty
Pump [8 45].
Order number DOC 2330426 | Edition 09/2021
35

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zip80

Table of Contents