IBC SL Series Installation & Operating Manual page 68

Commercial condensing boiler
Table of Contents

Advertisement

Check to see that adequate gas pressure is present at the inlet gas supply test port.
Connect a manometer and open the gas control valve. Requirements are minimum 4" w.c
and maximum 14" w.c.
Check that there are no gas leaks.
All connections are pressure tested and leak free.
All piping flushed to ensure all air is removed.
Check valve is installed and the external pump is flowing in the correct direction.
All connections are pressure tested and leak free.
All vent pipe is sized correctly and joints are sealed.
Perform a final check of electrical wiring, and provide power to the boiler to initialize
operation.
Warning
Fill the condensate trap with water before you first fire the boiler to prevent exhaust
fumes from entering the room. Never operate the boiler unless the trap is filled with
water. Failure to comply will result in severe personal injury or death.
Checking piping connections
Checking venting connections
Powering on the boiler
64
Section: Before operating the boiler
Check
Check
Check

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sl 26-260 g3Sl 40-399 g3

Table of Contents