Horizontal Infrared Toaster
IRT-SB-NA-1PS
IRT-SB-NA-3PS
Slide the conveyor belt back onto the conveyor
8
assembly. Previously removed in step 7
Re-install the right side panel of the conveyor
9
assembly by securing with (2) Phillips screws.
Previously removed in step 6.
Reinstall (4) nuts on the right side of the conveyor us-
10
ing an 8mm nut driver. Previously removed in step 5.
Reinstall all insulation on the right side of the conveyor
11
assembly. Previously removed in step 4.
Install the conveyor assembly onto the unit. Secure
12
using (2) Philips screws. Previously removed in step 3.
Reinstall the Motor. Reference the motor install on
13
page 17.
Plug in unit. Power on and ensure the unit is fully
14
functional.
IRT-SB-NA-1PS
IRT-SB-NA-3PS
Replace Wire Belt
25
Printed in USA 12/3/2020
353-567 Rev. B