iCAP 7000 Series ICP-OES Spectrometer
1.1 Installation Flow Diagram
Shipment moved to customer laboratory
Connect equipment and start purge
Demonstrate instrument use to customer
Watch Customer use equipment and advice
This installation flow and timescales are dependent on appropriate customer personnel and
facilities being available.
Page 4 of 14
Site guide conformation
15 minutes
Unpack shipment
60 minutes
Locate equipment on bench
60 minutes
Check packing list
15 minutes
120 minutes
180 minutes
Overnight day 1
Installation performance check
120 minutes
Customer familiarisation training
180 minutes
Overnight day 2
Customer applications training
Detailed as additional training
on customer order
Installation Details
Applications Chemist
where available