1. Roughly position the boiler (A) into its intended
installation location.
Check there is sufficient length on the pipes (E & K) to
and from the boiler to make connections.
Check the power cable (D) will reach the power outlet
socket,
the power cable must not be extended.
Make sure there is a 10mm air gap around the case
sides.
Check the boiler is accessible to your customer so
they can easily disconnect and remove the boiler for
maintenance.
When you are confident with the boiler location, mark it
with a pencil then continue.
2. Unscrew the transport caps (O & P) from the boiler
inlet and outlet (B & C).
3. Turn the boiler upside down and tip any residual testing water inside the tank into a sink.
4. Mark on the cabinet wall the fixing hole centres.
Ensure the hole centres are level horizontally, we
suggest centres of 90mm at a minimum height of
245mm from floor level in the cabinet.
The boiler must be fixed to secure point to
prevent accidental tipping of the boiler unit. The unit
weighs approximately 9 kg when filled with water so
the wall and fixing used must be appropriate.
Using the screws (M) and if needed plugs (N) provided
(or similar if not suitable for your surface material) drill
and screw the fixings to the marked hole centres. The
screw head will need to be about 5mm from flush to
allow you to mount the boiler.
5. Insert the ½" rubber meshed seal (H) into the ½" boiler
inlet (B), ensure the orientation of the seal is as shown.