Drilling Conduit Holes

This section describes how to drill AC and DC openings at the bottom of the Synergy
Manager for connecting the AC and DC conduits.
This procedure must be performed before mounting the Synergy Manager.
To open conduit drill guides:
 1. Ensure that the Safety Switch is set to OFF (0) and ON/OFF/P switch of the Synergy
Manager is in OFF position.
 2. Remove the screws securing the DC and AC panels and remove the panels from the
bottom of the Synergy Manager enclosure.
CAUTION!
To avoid damage to the internal part of the Synergy Manager, always
remove plates from unit before drilling holes.
NOTE
Unused conduit openings should always be sealed.
Three Phase Inverters with Synergy Technology
Chapter 3: Installing the Synergy Manager and Synergy Units
    29

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se50kSe66.6kSe55kSe80k

Table of Contents