SolarEdge SE K Series Installation Manual page 48

Three phase inverters with synergy technology
Hide thumbs Also See for SE K Series:
Table of Contents

Advertisement

USB cable: 3.3 ft (1 meter), USB-C to USB-C (not provided)
IMPORTANT NOTE
Commissioning should be performed in full daylight.
NOTE
When pre-commissioning multiple inverters, each inverter need to be
commission individually.
To pre-commission the inverter:
 1. Turn OFF and secure the AC circuit breaker in OFF position in the circuit breakers
panel.
 2. Verify that SolarEdge SetApp is installed on your mobile device.
 3. Turn the DC Disconnect Switch on the Synergy Manager to ON position (if
applicable).
 4. Remove the cover from the Power Bank input port at the bottom of the Synergy
Manager. Connect the USB cable between the Power Bank and the input port -
Upon connection, all LEDs light steady for one minute, and then alternate blue /
green.
NOTE
Alternating red / blue LEDs indicate a problem with the power bank.
 5. Start SetApp on your mobile device and follow the on-screen instructions.
Three Phase Inverters with Synergy Technology
Chapter 5: Activating, Commissioning and Configuring the System
Figure 26: Pre-commissioning the inverter