SolarEdge SE K Series Installation Manual page 62

Three phase inverters with synergy technology
Hide thumbs Also See for SE K Series:
Table of Contents

Advertisement

NOTE
Do not cross-connect B, A and G wires.
 7. Tighten the terminal block screws.
 8. Check that the wires are fully inserted and cannot be pulled out easily.
 9. Push the RS485 terminal block firmly all the way into the connector on the right side
of the communication board.
 10. Terminate the first and last SolarEdge device in the chain by switching a termination
DIP-switch inside the inverter to ON (move the left switch up). The DIP-switch is
located on the communication board and is marked SW1.
Three Phase Inverters with Synergy Technology
Chapter 6: Setting Up Communication with the Monitoring Platform
Figure 34: Connecting the inverters in chain
    61