Use a crimping tool to crimp the connector.
Connect the Ethernet connector to the RJ45 port on the communication board
as shown in Figure 30 .
For the switch/router side, use a pre-crimped cable or use a crimper to prepare an
RJ45 communication connector.
Connect the cable RJ45 connector to the RJ45 port of the Ethernet router or switch.
You can connect more than one inverter to the same switch/router or to different
switches/routers, as needed. Each inverter sends its monitored data independently
to the SolarEdge Monitoring platform.
NOTE
There are no LED indicators on the Ethernet connector, if the inverter is not
communicating with the Monitoring platform through a LAN refer to
"Troubleshooting Communication" on page 68
LAN Configuration
 1. The inverter is configured by default to LAN. If reconfiguration is required:
 a. Verify the ON/OFF/P switch is OFF.
 b. Verify the AC is on.
 c. Close the cover and turn ON the DC Disconnect Switch of the Synergy Manager.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when
the Synergy Manager cover is removed.
 d. Use the SolarEdge SetApp to access the Commissioning main menu screen as
described in "Activating, Commissioning and Configuring the System" on
page 43"Activating, Commissioning and Configuring the System" on page 43 .
 e. From the Commissioning screen, tap Communication.
 f. Select Configure Ethernet, to configure the connection.
Three Phase Inverters with Synergy Technology
Chapter 6: Setting Up Communication with the Monitoring Platform
    57