Offsetting Plastic Top Rail - Hussmann Excel FWG Installation & Operation Manual

Low temperature, single deck wall & island merchandisers
Table of Contents

Advertisement

I
1-20
nstallatIon

OFFSETTING PLASTIC TOP RAIL

Offsetting the plastic top rail helps to disguise
the joint locations, giving the lineup a smoother
look.
If factory installed, carefully remove all plastic
top rails in the lineup. Do not damage the top
rail retainer.
1. Refer to 1 in illustration below. Install a
1-ft starter section flush against the corner trim
at the left end of the lineup.
2. Refer to 2 in illustration below. Re-install
a 38-inch section removed earlier from the end
merchandiser. Place it flush against the starter,
without any gaps.
3. Refer to 3 in illustration below. Install a
full-length top rail, leaving no gaps. Continue
installing the top rails the length of the lineup.
P/N 0467434_P
4. Once all except the last section of top rail
have been installed refrigerate the merchandiser
lineup for at least six (6) hours. The last section
of top rail should be kept inside a cooler or
refrigerated merchandiser during this time. This
will allow the top rail to contract.
5. Go to the right end of the lineup and tap
the top rail to close any gaps.
6. Refer to 4 in illustration below. Measure
and cut last section of top rail. Use a miter
box and fine-tooth saw to cut last top rail to
length. Install the last section.
7. Remove protective film from top rail once
installation is complete.