Figure 7
Terminals X1, X2, X3
13
STARTING
Observe the plant-specific and process-specific safety measures before commissioning.
Note
The following steps must be carried out before initial commissioning:
1. Wiring the system cable before commissioning according to the circuit diagram
2. Connect heated line (optional);
Warning
3. Connect power to the system cables
4.
Switch circuit breaker 1 to position ON.
5. Switch circuit breaker 2 to position ON with optional sample gas line.
Carry out the following steps for commissioning:
1. Switch on the fuses/circuit-breakers of the gas treatment device
a. F2 heated sample tube. (self regulating)
b. F1 Gas cooler, sample gas pump, bellow valve pump, etc.
2. the gas conditioning unit is ready for operation after 45 minutes
3. Switch on –Q1 sample gas pump.
4. Set the sample gas flow at the regulating valve on the head of the sample gas pump to approx.
70 Nl/h.
24
Before connecting the mains voltage, the circuit breakers must be set to OFF.
When operating the sample gas conditioning system with a heated
sample gas line, the temperature must be checked at the temperature
controller.