Bottom Cable Routing - Huawei UPS5000-E Series User Manual

Hide thumbs Also See for UPS5000-E Series:
Table of Contents

Advertisement

UPS5000-E-(350 kVA–800 kVA)
User Manual (50 kVA Power Modules)

3.2.6.2 Bottom Cable Routing

Procedure
Step 1 Open the front door of the bypass cabinet and remove the covers of the power
distribution subrack.
Step 2 Remove the cable covers from the bottom of the cabinet, drill holes in the covers,
attach grommet strips to the hole edges for protecting cables, and reinstall the
cable covers.
The hole size and quantity are for reference only.
Figure 3-56 Removing the bottom cable covers and drilling holes
(1) Power cable covers
Step 3 Remove the rear cover from the bypass cabinet.
You are advised to remove the side panel from the bypass cabinet before connecting cables.
Step 4 Remove the copper bars between the mains and bypass input wiring terminals.
(Perform this step only when the mains input and bypass input use different
power sources.)
Issue 15 (2022-01-30)
NO TE
NO TE
Copyright © Huawei Technologies Co., Ltd.
(2) Signal cable hole
3 Installation
107

Advertisement

Table of Contents
loading

Table of Contents