Huawei UPS5000-E Series User Manual page 147

Hide thumbs Also See for UPS5000-E Series:
Table of Contents

Advertisement

UPS5000-E-(350 kVA–800 kVA)
User Manual (50 kVA Power Modules)
Figure 3-93 Positions to be checked for foreign matter (400 kVA)
(1) Switches
(4) Output wiring copper bar
Issue 15 (2022-01-30)
NO TE
1. In the scenarios where holes are drilled for routing cables or covers are removed for
routing cables, after routing cables and checking cable connections, use sealing putty to
fill in the gap between the cables and the cabinet.
2. After verifying the installation, reinstall all the covers.
3. Do not remove the dustproof cover before power-on to prevent dust inside the UPS.
Copyright © Huawei Technologies Co., Ltd.
(2) Mains input wiring copper
bar
(5) Bypass input wiring copper
bar
3 Installation
(3) Battery input wiring copper
bar
(6) Rear of modules
138

Advertisement

Table of Contents
loading

Table of Contents