5.3 Positioning
Positioning using a crane
5.4 Positioning at the installation site
5.4.1 Removing boiler from pallet
M1820921_en | Installation instructions Dual fuel boiler SP Dual compact
NOTICE
Damage to components if handled incorrectly
r Follow the transport instructions on the packaging
r Transport components with care to avoid damage
r Protect the packaging against damp conditions
r Pay attention to the pallet's centre of gravity when lifting
r Position a fork-lift or similar lifting device at the pallet and bring in the components
If the firewood boiler cannot be brought in on the pallet:
r remove the cardboard and take the boiler off the pallet
Ü "Removing boiler from pallet" [} 25]
If the pellet unit cannot be brought in on the pallet:
r Remove the cardboard and take the pellet unit off the pallet
Ü "Removing the pellet unit from the pallet" [} 27]
r Attach the crane hook to the attachment point correctly and position the boiler
r Lift the cardboard boxes for the insulation, controller and control off the pallet
Transport and storage | 5
25