If necessary, bundle the cables with additional Velcro straps to ensure that they stay clear
Note -
of other equipment. If you need to install additional Velcro straps, wrap the straps around the
cables only, not around any of the CMA components; otherwise, expansion and contraction of
the CMA slide bars might be hindered when the storage server is extended from the rack and
returned to the rack.
18.
Proceed to
Arm" on page
Related Information
"Verify Operation of Slide-Rails and Cable Management Arm" on page 53
"Remove the Cable Management Arm" on page 55
Verify Operation of Slide-Rails and Cable Management
Arm
Use the following procedure to ensure that the slide-rails and CMA are operating correctly.
Two people should perform this procedure: one to move the storage server in and out of
Note -
the rack, and one to observe the cables and CMA.
To prevent the rack from tipping forward when the storage server is extended,
1.
extend all rack anti-tilt devices.
To reduce the risk of personal injury, stabilize the rack cabinet and extend all anti-tilt
Caution -
devices before extending the storage server from the rack. For instructions for stabilizing the
rack, see
"Stabilize the Rack for Installation" on page
2.
Slowly pull the storage server out of the rack until the slide-rails reach their
stops.
Inspect the attached cables for any binding or kinks.
3.
Verify that the CMA extends fully with the slide-rails.
4.
To return the storage server back to the rack:
5.
"Verify Operation of Slide-Rails and Cable Management
53.

Verify Operation of Slide-Rails and Cable Management Arm

29.