To pull the green release tabs, place your finger in the center of each tab, not on the end,
Note -
and apply pressure as you pull the tab toward the front of the storage server.
Continue pushing the storage server into the rack until the slide-rail locks
b.
(located on the front of the storage server) engage the slide-rail assemblies.
You will hear an audible click when the storage server is in the normal rack position.
15.
Connect cables to the storage server, as required.
Refer to the Oracle Exadata Database Machine documentation for instructions.
Power cables should already be installed in the Sun Rack II 1042 (1000-mm) system
Note -
rack.
16.
Open the CMA cable covers, route storage server cables through the CMA's
cable troughs, close the cable covers, and secure the cables with the six Velcro
straps.
Route the cables through the cable troughs in this order:
Install the Cable Management Arm